148th Ave NE & NE 51st St Pavement Repairs

Location: See map below

Project Phase: Construction Complete

Project Manager: Patty Criddle, 425-556-2723

Page Last Updated: 12/11/17

Description:

Paving work is completed on:

  • 148th Ave NE from the SR 520 Bridge to NE 36th Street
  • NE 51st Street from 148th Ave NE to 156th Ave NE

Both the 148th Ave NE Pavement Preservation project and the NE 51st Street Pavement Preservation project were federally funded. Each project rehabilitated approximately half-a-mile of deteriorating pavement. Construction on both roadways included:

  • Grinding and resurfacing the roadway curb to curb with hot mix asphalt   
  • Constructing curb ramps to current ADA standards  
  • Signal loop replacements

The NE 51st Street project also included:

  • Repairing fatigued pavement areas
  • Lane rechannelization
  • Replacing damaged and deteriorated storm water pipes
  • Upgrading sanitary sewer manhole lids


New pavement on NE 51st Street
  NE 51st St at SR520, looking west

New pavement on 148th Ave NE
  148th Ave NE at SR520, looking north


Community Outreach Materials
Postcard Mailer
148th Ave NE Flier - July 14, 2017
NE 51st St Flier - July 14, 2017

148th Ave & NE 51st Pavement Repair Project Location Map